Installation and Dismantling of a Power Plant Equipment

Dismantling and installation works on a hot water boiler PTVM-100 No 2 pipe screens, air ducts, platforms and pipelines. Power 116,3 MW, capacity 100 t/h, temperature 70°C-150°C, pressure P-25 bar

Customer and object:
Vilniaus šilumos tinklai UAB. Vilnius Power Plant E-2

Place and time:
Vilnius, Lithuania. 2018